Smt. Darshana Jardosh inspects Mumbai Ahmedabad High Speed Rail Corridor construction activity between Surat & Vapi

0
481
Smt. Darshana Jardosh
The Minister of State for Textiles and Railways, Smt. Darshana Vikram Jardosh addressing at the 7th National Handloom Day, in New Delhi on August 07, 2021.
0 0
Azadi Ka Amrit Mahoutsav

InterServer Web Hosting and VPS
Read Time:1 Minute, 44 Second

by PIB Delhi

Smt. Darshana Jardosh, Minister of State for Railways and Textiles today inspected the work of Mumbai – Ahmedabad High Speed Rail at project site between Surat and Vapi.

Hon’ble Minister started the visit with Casting yard at Ch. 243 in village Padgah, District Navsari for inspection for preparatory works of casting of girder planned for castings including casting of Pile cap at Ch. 242 P42 & P23.

Next stop was Casting yard at Ch. 238 (Village Nasilpore, Dist Navsari) where she witnessed display of heavy equipment like straddle carrier of capacity 1100 T and bridge gantries.

Another casting yards visited by Hon’ble Minister were Casting yards at Ch. 232 (Village Kachchol, Dist Navsari) witnessing casting of full span girder, operation of ready-made steel plant (RMS) Plant, automatic cutting of steel and Ring/stirrup making plant and inspection of viaduct piers from Ch. 197 to 195 in village Pathri District Valsad.

At the end, Hon’ble Minister also visited the Daman Ganga river site where Foundation of river bridge is taking place.

Additional Information:

Some salient points of MAHSR construction activity are:

· In Gujarat state (352km), 100% Civil Tenders have been awarded to Indian Contractors.

· 98.6% land has been acquired and Civil construction work has started in entire 352km.

· In Gujarat state (352km), 98.6% land has been acquired and Civil construction work has started in entire 352km. In Maharashtra, 62% land has been acquired.

· The works on Piles, Foundations, Piers, Pier Caps, casting & erection of Girders for Viaduct & Stations have started all along the alignment passing through 8 districts of Gujarat.

· Out of 352 km, Geotechnical Investigation work has been completed in 325 km length.

· For doing the Geotechnical Investigation, Asia’s largest Geotechnical Lab has been developed at Surat.

· Construction work of Piles, Pile Caps, Open Foundations, Well Foundations, Piers, Pier Caps is in progress in 110 km length.

· Out of 352 km, Piling has been completed in 81 km length, Foundation have been completed in 30 km length and Pier have been completed in 20 km length.

About Post Author

Suman Munshi

Founder Editor of IBG NEWS (15/Mar/2012- 09/Aug/2018). Recipient of Udar Akash Rokeya Shakhawat Hossain Award 2018. National Geographic & Canon Wild Clicks 2011 jury and public poll winner. Studied Post Graduate Advance Dip in Computer Sc., MBA IT,LIMS (USA & Australia), GxP(USA & UK),BA (Sociology) Dip in Journalism (Ireland), Diploma in Vedic Astrology, Numerology, Palmistry, Vastu Shastra & Feng Sui 25 years in the digital & IT industry with Global MNCs' worked & traveled in USA, UK, Europe, Singapore, Australia, Bangladesh & many other countries. Education and Training advance management and R&D Technology from India, USA, UK, Australia. Over 30 Certification from Global leaders in R&D and Education. Computer Science Teacher, IT & LIMS expert with a wide fan following in his community. General Secretary West Bengal State Committee of All Indian Reporter’s Association
Happy
Happy
0 %
Sad
Sad
0 %
Excited
Excited
0 %
Sleepy
Sleepy
0 %
Angry
Angry
0 %
Surprise
Surprise
0 %
Advertisements

USD





LEAVE A REPLY

Please enter your comment!
Please enter your name here