Indian Railways Kavach Progress Reviewed by Railway Minister – Latest Update

0
41
Indian Railways Kavach Progress Reviewed by Railway Minister – Latest Update
Indian Railways Kavach Progress Reviewed by Railway Minister – Latest Update

Railway Minister Reviews Progress of Kavach Implementation


Indigenous Universal Braking Algorithm Developed under Kavach by Railways to Help in Faster Implementation of Kavach 4.0

AI Based Centralised Monitoring Platform, “Suraksha” under Kavach will Alert Traffic Monitors for Unusual Events & Thus Help Ensure Our Safe Journey by Their Timely Action

Posted On: 26 MAR 2026 6:13PM by PIB Delhi

Union Minister for Railways Shri Ashwini Vaishnaw reviewed the progress of Kavach, the indigenously developed Automatic Train Protection (ATP) system of Indian Railways. The meeting focused on accelerating deployment, and leveraging advanced technology to ensure  more efficient train operations.

Technological Advancements Driving Kavach

Indian Railways has introduced several cutting-edge enhancements in Kavach. The Universal Braking Algorithm (UBA), which standardizes braking curves across different manufacturers, ensures interoperability and eliminates repetitive trials. Significant upgrades in baseline software, AI-driven design automation, and integration interfaces for locomotives, interlocking systems, and track machines are further strengthening system robustness.

A centralized monitoring platform, SURAKSHA, is being developed as a unified Operations Management System to enable real-time monitoring, and predictive maintenance of Kavach installations.

Progress So Far

So far Kavach has been installed on 3,103 Route Km. Kavach Work is currently in progress on 24,427 route kilometers, including high-density and high-utilization corridors.

As part of Version 4.0 deployment:

  • 1,638 route kilometers have already been commissioned on key corridors such as Delhi–Mumbai and Delhi–Howrah.
  • Recently, Indian Railways has commissioned Kavach on 190 Route Kilometres of Prayagraj–Kanpur Section of Delhi–Howrah High-Density Corridor.
  • 7,100 route kilometers have trackside installations underway.
  • Optical Fiber Cable (OFC) has been laid over 8,921 km, supported by 1,183 telecom towers and Kavach Data Centres installations across 767 stations.
  • Kavach has been installed on 4,277 locomotives.
  • Work is in progress on 8,979 locomotives.

Expansion Plans

Kavach installation is a complex process. To further expand its implementation, Railway is planning to expand Kavach network by 9,000 Route Km in next two years and thereafter it is expected to grow upto 10,000 Route Km per year.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Adblocker detected! Please consider reading this notice.

We've detected that you are using AdBlock Plus or some other adblocking software which is preventing the page from fully loading.

We don't have any banner, Flash, animation, obnoxious sound, or popup ad. We do not implement these annoying types of ads!

We need money to operate the site, and almost all of it comes from our online advertising.

Please add https://www.ibgnews.com to your ad blocking whitelist or disable your adblocking software.

×
Verified by MonsterInsights